The Get Probe Assembly command is an operation used to switch the active probe configuration during part programming or execution.
When CMM-Manager encounters a Get Probe Assembly command in the program database, it retrieves the stored calibration and geometric data for the selected probe build, updates the graphics display, and activates that probe assembly for subsequent measurements.
Key Capabilities and Behavior
- Automated Probe / Tool Changing: If your CMM is equipped with a calibrated probe station (changing rack such as an MCR20, SCR200, ACR3, or FCR25) and the requested probe assembly is assigned to a port, CMM-Manager will automatically drive the CMM to the rack to dock the current probe/module and pick up the new one.
- Manual Tool Swap Prompts: If the target probe assembly is not assigned to a rack port or no probe station is present, CMM-Manager halts program execution and displays a pop-up prompt instructing the operator to manually attach the designated probe assembly before continuing.
- Command Insertion: When in Teach-On Mode, executing this command inserts a Get "Probe Assembly Name" command into the Program Database directly below the current cursor. This occurs even if the requested probe assembly is already active (i.e., no physical probe change is required). During program execution or playback, when the machine reaches this command, it checks the active probe assembly and performs a probe change if necessary.
- Prerequisite: The Get Probe Assembly button is only enabled when more than one Probe Assembly has been defined in the Probe Assembly list.
How to Use the Get Probe Assembly Command
- Launch the Command: Select the Probe tab on the ribbon bar, locate the Probe group, and click Get Probe Assembly.
- Select the Target Probe: In the pop-up window, choose the desired probe assembly name from the Get: drop-down menu.
- Confirm the Action: The Operations text box inside Get Probe Assembly window displays the sequence of physical steps that CMM-Manager will perform to switch to the selected probe assembly. Depending on your probe setup and selection, the text box will display the following:
- NONE: Displayed when no physical change or machine motion is required—such as when you select the probe assembly that is already currently active.
- Automated Rack Operations: When automatic probe stations or changing racks (such as an MCR20, SCR200, or FCR25) are configured, it lists the automated movement sequence, such as driving the CMM to a specific port to unload the current module and moving to another port to load the new one
- Manual Change Steps: If the requested probe assembly or stylus module is not assigned to an automated rack port, it indicates that manual operator intervention will be required during execution.
- Confirm: Click OK. The sequence of actions specified in the Operations text box will be executed.
When writing automated programs that switch tools, always ensure the CMM has a clear, obstruction-free path to the probe rack's safe position before issuing a Get Probe Assembly command. You may need to insert intermediate clearance move points or manually move the probe prior to the tool change command to prevent the probe body or extension from colliding with part fixtures or other obstacles on its way to the rack.